2. The following fields must be filled in, regardless of whether you press the button to add a modification in the budget module or in the Change order module.
Job Work number - This is the sequence number of the Change order. You can set it yourself or use the automatic numbering provided by Bauwise. For this example, I use automatic numbering.
...
Date - The date of the change order.
...
3. To add a new job work line, press the "Add new line" button:
...
4. After pressing the button, a new line without a job work code will appear:
...
5. By clicking on the green cell in the "subcontractor contract" column, a list of all project contracts will appear where work can be assigned. In this case, there is only one contract - "001 Design works". If the added work is not related to any contract, it must be assigned under unsigned contracts.
...
6. Since it is a new job work that is not yet in the budget, a unique job work code must be assigned to the job work that does not exist in the budget. In this case, I enter 0001 and press "Add new job work code 0001":
...
7. Next, I name the jobwork, in this example "Junk house foundation" and determine the cost. Since the work falls under unsigned contracts, we do not have a Subcontractor, the cell "Subcontractor Budget" cannot be filled in.
...