Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

It is possible to sort them according to the status (in the blue circle):

Pending - Additional and modification work Change order is in the preparation stage. Lines of additional and modifcation work change orders are not reflected in the budget.

Sent for confirmation - Additional and modification work Change order has been sent to the Customer. Lines of additional and modification work the change order are not reflected in the budget.

Confirmed - Additional and modification work Change order has been confirmed by the Client. Additional and modification work Change order is reflected in the budget.

Rejected - Additional and modification work Change order has been rejected by the Client. Additional and modification work Change order is not reflected in the budget.

All - All additions and modifications change orders are visible, regardless of status.

...

Explanations of the table columns (in a yellow circle):

Open modification workchange order - By clicking on the folder, it is possible to open additional and modification works change orders and see their contents. A new window will open.

Type - By adding modificationschange orders, you can specify their type and sort based on it.

Job No. - No. is determined by adding a modification change order or automatic numbering is used (recommended).

Description - Description of the content of the modificationchange order.

Date - The date of the modificationchange order.

Cost estimate - Cost estimate of the work to be done to implement the modification change order (direct cost/target budget).

Revenue estimate- The fee received from the Customer for the implementation of the modification change order (sale price).

Status - The status of the modification change order (pending, sent for confirmation, confirmed, rejected).

...

There are 3 options for adding additions and modificationschange order:

  1. Adding additions and modifications change orders to existing job work codes

  2. Adding a modification change order with a new job work code

  3. Copy of Copy of Kombineeritud lisa- ja muudatustöö lisamine Adding combined change orders