Change orders

All additions and changes are displayed in this view.

It is possible to sort them according to the status (in the blue circle):

Pending - Change order is in the preparation stage. Lines of change orders are not reflected in the budget.

Sent for confirmation - Change order has been sent to the Customer. Lines of the change order are not reflected in the budget.

Confirmed - Change order has been confirmed by the Client. Change order is reflected in the budget.

Rejected - Change order has been rejected by the Client. Change order is not reflected in the budget.

All - All change orders are visible, regardless of status.

Explanations of the table columns (in a yellow circle):

Open change order - By clicking on the folder, it is possible to open change orders and see their contents. A new window will open.

Type - By adding change orders, you can specify their type and sort based on it.

Job No. - No. is determined by adding a change order or automatic numbering is used (recommended).

Description - Description of the content of the change order.

Date - The date of the change order.

Cost estimate - Cost estimate of the work to be done to implement the change order (direct cost/target budget).

Revenue estimate- The fee received from the Customer for the implementation of the change order (sale price).

Status - The status of the change order (pending, sent for confirmation, confirmed, rejected).

 

There are 3 options for adding additions and change order:

  1. Adding change orders to existing work codes

  2. Adding a change order with a new work code

  3. Adding combined change orders